Checklist of inspections

The complete monitoring of a wind turbine through regular maintenance, inspection and repair, as well as regular independent appraisals, are prerequisites for ensuring the best possible operational safety.

Find out here which mandatory inspections are due in which operating year of your wind turbine

Required safety checks

according to Standards

  • LoremIpsum
  • LoremIpsum
  • LoremIpsum
  • LoremIpsum
  • LoremIpsum

Commissioning WEA

on commissioning

Winches, lifting and pulling equipment

annual

Drive-on systems/lift (ZüS)/IBN/Z/H

annual

Security technology

annual

This applies to the testing of ladders, climbing protection, protective equipment (PPE), anchor points, access equipment and winches, for example.

Inspection before the end of the warranty

2 years after commissioning

Im Regelfall fällt die Prüfung vor Ende der Gewährleistung 2 Jahre nach Inbetriebnahme an, je nach vertraglicher Vereinbarung kann die Gewährleistung allerdings auch bis zu 5 Jahre betragen.

Fire-fighting equipment

Every 2 years

Marking/signage

Every 2 years

Lightning and surge protection

Every 2 years

A comprehensive inspection for lightning and surge protection is necessary every 2 years. A visual inspection of the earthing and lightning protection system should additionally be provided annually.

Periodic inspection WEA

Every 4 years

Electrical equipment DIN IEC 60364/DGUV V3

Every 4 years

Protective device testing

Every 4 years

Pressure equipment (ZüS) - Exchange

At commissioning and 10 years after commissioning

Continued operation

20 years after commissioning

Condition-based testing WEA

There are no set deadlines for the condition-based inspection. Please contact us for further information.